Despite an additional £200,000 being secured to carry out flood prevention work in Binstead, progress to protect the village remains incredibly slow with properties still at risk of more devastating damage. In April 2022, £170,000 was ringfenced by the Isle of Wight Council for flood mitigation works to be carried out in Binstead. However, projections have skyrocketed since with more than double the amount of money now needed to ensure a successful scheme. It’s said that previous assessments of the work needed to be undertaken were ‘inadequate’ and had not been brought up to date to reflect increased costs. Furthermore, utility restraints and ‘other hurdles’ have led to increased costs. An additional £200,000 of funding from the Environment Agency was secured by the Isle of Wight Council in November last year to enable the project to move forward, topping up the £170,000 already allocated in the local authority’s budget. But in the 4 months that have followed, very little has actually occurred – nearly 3 years after the devastating floods of July 2021. 18 months ago, local ward councillor Ian Dore said “now we have the data and importantly the funding, we can light the touch paper and blow the doors off!”. But the reality has been less dramatic. 

”At the time of my statement, it was based on the facts that I had. In this case, not so much as a firecracker went off. Let me explain why. “In this specific instance it turns out it was down to two things; a utility issue (where the SUDS were considered at one point) and funding. This resulted in the project costing a lot more. Due to lack of Government funding and investment, this had to be secured. There have been curveballs and challenges thrown up from the outset and its incredibly regretful. Especially when you are essentially the spokesperson. I can help secure funds, but I can’t force a digger to dig. “I’ve learnt in Council land that you don’t get a coconut every time. Residents should be reassured though; we continue to throw the balls until they are all knocked off. Those funds are secured to a total value of £1.3 million and they are trying to get the spades in the ground as soon as possible, along with the PFR elements”.
Reassuring local residents, Cllr Dore has said:
”Through the recent Alliance Budget, the council have set aside additional monies in the 2024/25 budget which will be spent on extra gulley cleaning in the areas prone to flooding on the Island, such as Binstead. The council will negotiate the extra gulley cleaning regime directly with Island Roads in the coming weeks. “The Property Flood Resilience (PFR) scheme, using previous Section 19 investigations as an evidence base, will provide fully funded flood resilience measures to identified properties that have suffered internal flooding. The first step will be undertaking surveys on individual properties to work out what kind of resilience measures may be appropriate. The IWC & EA will be contacting property owners in the coming weeks to start this process. “In mid to late April, there will be another Public Meeting at Binstead Community Centre, where residents can attend and ask questions of the appropriate stakeholders. Already confirmed is the Leader of the Council and Isle of Wight Council Planning. We are awaiting confirmation from the EA and Southern Water, as well as Island Roads. Once confirmed, the date will be shared appropriately. “I don’t have all the answers, I am often simply the spokesperson. The one that takes the flak, the man on the ground. These are the people that have the intricate answers so please come along and engage”.





























































































Don’t they have water butts I thought, they should be fine then.
Not that many
Been flooded twice in 3 years, Im still waiting for mine. Also waiting to hear back about grant for flood proof doors, air vents etc.
It’s bad enough trying to get the council to move on anything but a joint scheme like this will make it very easy for each agency to blame the others for slow progress.
I’m sure if it was the council office that was getting flooded it would have been sorted years ago
Of course it’s slow, it’s something the council tax payers need
I think they’ll turn all the banknotes into paper mache and mould then into some kind of door seal to help keep the water out. This seems to be the best suggestion so far.
Water butts?
So, the water butt fills up after a heavy downpour, what happens when it rains again? The water goes down the drain as before and the area floods again.
Water butts are fine during the summer months as they save you using water from the taps, but anyone who uses them will know that they fill up in no time with all the rainwater coming off a house roof etc.
We’ve got about 4 dotted around the garden, and they’re all full at the moment.
You need to fix the problem, not put a sticky plaster over it. Clear the drains, don’t build on flood plains, stop building so many new houses, these are the things that matter, not handing out water butts.
And how are we to combat the root cause, climate change? Or we still pretending that is fake. Also, Binstead is not a flood plain. Don’t matter how many ‘clean’ drains you have if we get a months rain fall in one night.