Wightlink will be carrying out essential maintenance work at its berth at Fishbourne port from Monday 29th March until Friday 14th May 2021.
Aging fenders will be replaced with new ones in 4 weeks of overnight work, scheduled to take place when tides permit.
Chief Executive Keith Greenfield says:
“Our contractors will do their best to keep disturbance to a minimum but unfortunately, there may be some noise. We apologise in advance if this causes any inconvenience to our neighbours in Fishbourne.”
Contractors will be based on a barge offshore during the operation. The replacement work will be suspended if winds rise over 25 knots.
Schedule of fender works at Fishbourne
| Monday 29th March – Friday 2nd April | Berthworks 20:00-05:00 |
| Monday 5th April – Friday 9th April | No works because of tides |
| Monday 12th April – Friday 16th April | Berthworks 20:00-05:00. The 23:00 and 01:00 sailings from Fishbourne will be cancelled on 13th and 14th April |
| Monday 19th April – Friday 23rd April | No works because of tides |
| Monday 26th April – Friday 30th April | Berthworks 20:00-05:00 |
| Monday 3rd May – Friday 7th May | No works because of tides |
| Monday 10th May – Friday 14th May | Berthworks 20:00-05:00. The 23:00 and 01:00 sailings from Fishbourne will be cancelled on 11th and 12th May |