More than £52million is set to be invested in tackling storm overflow releases across the Isle of Wight over the next decade, as Southern Water admits it needs to go ‘harder and faster’ in addressing sewage spills and improving the Island’s water infrastructure.
The water company has outlined a long-term improvement plan covering 2025-2035, including upgrades to pumping stations, water supply networks and wastewater infrastructure, alongside measures to reduce pollution and strengthen resilience against power outages.
More than £20million of investment has been brought forward to accelerate investigations into storm overflows, with Southern Water acknowledging that significant work is needed to reduce the amount of surface water entering the sewer network during heavy rainfall.
The company says there is no single solution to tackling storm overflows, with different locations requiring different approaches to prevent sewer networks becoming overwhelmed.
Investigations at 9 storm overflows across the Isle of Wight were brought forward to April 2026, allowing potential problems to be identified and solutions developed sooner than originally planned.
Lawrence Gosden, Chief Executive Officer of Southern Water, has said:
“We’ve heard clearly that we need to go harder and faster on reducing the impact of storm overflows on the Island – and I agree.
“A major challenge is the amount of rainfall and surface water entering parts of the sewer network. That’s why we’ve brought forward more than £20 million of investment to accelerate investigations and identify the right long-term solutions for each location.
“We’re making a historic investment to deliver a generational change in the Isle of Wight’s water and wastewater infrastructure. While meaningful change won’t happen overnight, this plan sets out the action needed to deliver lasting benefits for customers and the environment.
“Collaboration is going to be crucial – we’re listening to the Isle of Wight Council and local communities and want to continue working closely to tackle these challenges together.
“We understand that people will judge us not by what we say, but by what we do. Work is already under way across the island – we’re committed to delivering these improvements and being open about our progress every step of the way.”
Among the planned improvements is the replacement of more than 13km of water mains to reduce the risk of supply interruptions and improve reliability for customers.
Upgrades are also planned at Calbourne Water Supply Works, while Carisbrooke Water Supply Works will benefit from strengthened power and communications systems to reduce the likelihood of outages.
Investigations are continuing into rising mains at Appley Park and Springhill, with improvement plans to be confirmed once the work has been completed.
At Wroxall Wastewater Treatment Works, improvements are planned to remove more nitrogen from treated wastewater as part of wider efforts to improve river water quality.
Southern Water will also contribute to the Environment Agency’s coastal defence projects at Yaverland and Ventnor.
A further 25 wastewater pumping stations across the Isle of Wight are set to benefit from resilience improvements.
These include pollution reduction measures at 15 sites near bathing waters, alongside upgraded backup power supplies at 10 locations to minimise disruption caused by electricity failures.
The company has also highlighted improvements already delivered across the Island such as at Solent Landings in Bembridge, where flood barriers have been installed to provide additional protection for properties while a longer-term solution to reduce flood risk is developed.
Smart sewer technology installed at Terminus Road in Cowes has also been credited with significantly reducing storm overflow use.
According to Southern Water, the number of recorded spills at the site fell from 79 in 2023 to just 3 in 2024, followed by 5 in 2025 and 2 so far in 2026.
Substantial improvements have also been completed at Albany Road pumping station, addressing concerns previously raised locally and improving the site’s condition and resilience.
Councillor Karen Lucioni, Chair of the Isle of Wight Council’s Environment and Community Protection Committee, has welcomed the investment commitments but stressed the importance of delivering tangible improvements.
Councillor Lucioni has said:
“We welcome Southern Water’s commitment to significant investment and the recognition that progress is needed, particularly in reducing the impact of storm overflows.
“Island residents have made it clear to us councillors that they expect to see improvements in reducing the impact of storm overflows and infrastructure resilience.
“We welcome work already beginning on the Island and the commitment of more than £52m being invested on reducing storm overflow releases.
“The council will continue to work with Southern Water, seeking regular updates to ensure these commitments bring improvements for our communities and environment.”
The investment programme covers both the current regulatory period from 2025-2030, known as AMP8, and the following period from 2030-2035, known as AMP9.
Southern Water has emphasised that the proposals include a mixture of approved projects and longer-term ambitions, meaning some future schemes remain subject to development and regulatory decisions.
The company says it will continue working with the Isle of Wight Council and local communities as the programme progresses, with a commitment to providing updates on the improvements being delivered.