FIRST PHASE OF FISHBOURNE LANE ROAD IMPROVEMENTS TO BEGIN NEXT WEEK


Island residents are being reminded that the first phase of a major road improvement scheme is due to start on Fishbourne Lane next week.

The work to Fishbourne Lane, one of the key gateway roads to the Isle of Wight, will see the road reconstructed and resurfaced in three phases either side of the main summer holiday period to avoid peak travel periods.

In the initial phase, starting on 15th July, preparatory works will be undertaken from its junction with Elenors Grove to the Wightlink terminal, to ensure the area is ready for the main phase of work in the Autumn. This first phase will involve carriageway reconstruction work and will be carried out during daytime hours over a 5-day period (15th to 19th July). The road will remain open during the works using temporary, manned traffic signals to help keep traffic flowing freely along the road. While all steps are being taken to minimise disruption, delays may be possible, and people are advised to allow more time for their journeys in the surrounding area.

Article continues below this advertisement

Residents and local businesses in the immediate vicinity of the work have been contacted ahead of the works. This follows a previous letter drop, site visits and two drop-in sessions earlier in the year at which residents were able to discuss the work and sign up for email updates during the scheme.

Stephen Ashman, Island Roads’ service director, said:

“Fishbourne Lane has deteriorated significantly over time and this work will help address the underlying issues that have caused this and improve and upgrade the road for everyone using it.

“It has not been an easy scheme to schedule, given the challenges of the road being both in a residential area and carrying a high volume of traffic flow to and from the ferry terminal and other businesses in the area, but we hope that by undertaking the scheme in three phases, we can help to minimise disruption for all concerned.

“We would like to thank businesses and residents in advance for their support in enabling us to carry out these works.”

Article continues below this advertisement

The main phase of the reconstruction works will take place in the Autumn in 2 phases starting Monday 2ndSeptember and due for completion by the beginning of November.

Works can be affected by external factors such as the weather and, as such, are subject to change.

Information boards on site will be kept updated to alert residents to any change in timescales and a dedicated section on the home page of Island Roads website www.islandroads.com will also provide the latest information.

Wightlink are also reminding customers that they need to arrive at the ferry terminal no less than 30 minutes but no more than 1 hour before their ferry departure time.

Timetable of works

Phase 1: Monday 15th July to Friday 19th July (1 week before school holidays, work under temporary traffic signals, manned during daytime hours to optimise traffic flow)
Phase 2: Monday 2nd September to Friday 27th September (1 week outside of school holidays, work under temporary traffic signals, manned during daytime hours to optimise traffic flow)
Phase 3: Monday 30th September to Friday 1st November (5 weeks, road closure night-time only, shorter shifts to assist with ferry timetable and local business and resident access).

No work will be carried out on Saturday and Sunday nights.

The views/opinions expressed in these comments are solely those of the author and do not represent those of Island Echo. House rules on commenting must be followed at all times.

2
Comment on this story

avatar
newest oldest most voted
JHVF
Guest
JHVF

Sounds to me that it’s spot on for the holiday season !!

bobiow
Guest
bobiow

As I would suggest over 90% of the traffic using Fishbourne Lane is from the car ferry, that the Ferry company should pay 90% of the cost involved, I mean no road, no car ferry ?? And they do charge enough

data-matched-content-ui-type="image_card_stacked"

News, Traffic & Travel Tweets